What is the first step in the installation of Runoff Diversion Measures?

Study for the Certified Erosion Prevention and Sediment Control Inspector Test. Prepare with multiple-choice questions, flashcards, and detailed explanations. Ace your exam!

The first step in the installation of Runoff Diversion Measures involves clearing and grubbing all trees, brush, and other objects in the path of the diversion. This step is crucial as it prepares the area for the effective installation of erosion control measures. By removing obstructions, you can ensure a clear path for the runoff diversion system to function properly, allowing for better water management and reducing the potential for erosion and sedimentation downstream.

Clearing the site also helps in identifying the topography and potential drainage patterns that need to be addressed. This step ensures that the subsequent installation of measures will be effective and that drainage structures can be positioned accurately to manage runoff and protect the site. Proper preparation is foundational for successful erosion control practices and helps minimize complications during and after installation.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy