Which of the following is a method for controlling dust from disturbed soil?

Study for the Certified Erosion Prevention and Sediment Control Inspector Test. Prepare with multiple-choice questions, flashcards, and detailed explanations. Ace your exam!

Using project phasing is a method for controlling dust from disturbed soil because it involves breaking up the construction or land disturbance project into smaller, more manageable stages. By doing so, only specific areas are disturbed at any given time, reducing the overall surface area exposed to wind and erosion and, consequently, minimizing dust generation. This approach not only helps in controlling dust but also allows for more effective management of sediment and erosion, as disturbed areas can be promptly stabilized before moving on to the next phase.

Effective dust control is critical in construction and land disturbance activities, as dust can pose health risks and contribute to environmental degradation. Project phasing allows for better oversight and implementation of dust control measures, which may include dust suppressants, vegetative cover, or other management practices specifically aimed at preventing dust emissions.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy