Which of the following is NOT a responsibility of a primary permittee?

Study for the Certified Erosion Prevention and Sediment Control Inspector Test. Prepare with multiple-choice questions, flashcards, and detailed explanations. Ace your exam!

The primary permittee in the context of erosion prevention and sediment control typically has specific responsibilities outlined under the National Pollutant Discharge Elimination System (NPDES). Among these, submitting the Notice of Intent (NOI), ensuring compliance with the Storm Water Pollution Prevention Plan (SWPPP), and conducting regular inspections are integral duties that help manage and mitigate stormwater pollution.

Submitting the NOI is important as it formally initiates the permitting process for discharges. Ensuring compliance with the SWPPP is essential to prevent discharges that could harm water quality, as this plan outlines the measures taken to control erosion and sedimentation. Conducting regular inspections is critical as it allows the permittee to evaluate the effectiveness of the implemented controls and address any deficiencies.

In contrast, issuing NPDES permits is not a responsibility of the primary permittee. This action is typically carried out by regulatory agencies, such as the Environmental Protection Agency (EPA) or state authorities, which establish the legal framework governing discharge permits. The role of the primary permittee is centered around compliance and implementation of the requirements set forth in their permit, rather than the issuance of permits themselves. This distinction clarifies why NPDES permit issuance is not a function of a primary permittee

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy